Entering performance tracking measures in a Threshold project

In Threshold projects, you can enter planned items that you want to track over the life of the project. For example, let's say your organization wants to track the number of hospital beds that will be added as a result of a specific project.

To enter performance tracking measures in a Threshold project:

  1. Open or create a Threshold project.
  2. In the Financial tab, click the Financial Statements tab.

  3. In the Performance Tracking Measures section at the bottom of the page, complete the following for each measurement you want to track:
    1. In the Input Format field, type the measure name. For example, Number of Beds.
    2. From the drop-down, select the measure value type to track.
    3. In the current year column (the first year column) and for each subsequent year, type the value to track.

  4. Click Save.

The measure you enter here are included in the Retrospective Comprehensive Update report.